NEWS | SOFTWARE | SHEET

Download the excel sheet to make analysis of Rates of Building Construction

To find out the building construction rates, a specific work item from labours’ and materials’ quantities needed with their outlay.

The labours’ and materials’ charges vary around, hence the rates of various work items vary around.

Each estimate must be along with the rate analysis of the items given in it.

Rate analysis includes:

  • Material Cost
  • Labour Cost
  • Sundries and Tools & Plants
  • Delivery
  • Service Provider’s Earnings

Tools & Plants is equal to 2.5 to 3 percent of the labour outlay.

Transportation outlay over 8 km is contemplated.

  • Water charges equal to 1.5 to 2 percent of overall outlay
  • Service provider’s earnings is equal to 10 percent

Labours’ and materials’ rates:

  • First class bricks = INR 4500 for each 1000 numbers.
  • Second class bricks = INR 4000 for each 1000 numbers.
  • Brick Ballast is equal to INR 800 for each m3
  • Coarse sand is equal to INR 800 for each m3
  • 50 kg cement bag is equal to INR 270 for each bag
  • Twisted bars equal to INR 5000 for each quintal

Bitumen equal to INR 10 for each kg

Mason = INR 550 for each day

  • Plaster equal to INR 300 for each day
  • Carpenter = INR 500 for each day
  • Bhishti = INR 350 for each day
  • Mazdoor = INR 350 for each day
  • Painter = INR 400 for each day

To download the excel sheet, click on the following link Rates of Building Construction

Earthwork in digging:
33 Mazdoor
(Percent m3) Mason = 1.5
Earthwork in Filling: 18 Mazdoor
(Percent m3) Mason = 0.5
Cement concrete: 15 Mazdoor

Visit more information this article onlinecivilforum.com

Download the excel sheet to make analysis of Rates of Building Construction