Estimation of RCC Framed Building

In the plan, there’re two rooms with size 3.5 x 3.5. There’re 6 six columns. Column width = 1 m. Excavation is going to be done up to the ground level. Overall height up to the ground level is 1.5 m. Excavation is going to be done of 1 m.

Earthwork in excavation in foundation.

Initial measure is to compute the overall centerline between the two columns.

Distance = 3.5 m

Column size = 0.3 m

Hence, center to center distance = 3.5 m + 0.3 m/2 x 2 = 3.8 m

From another center to center, overall centerline of 4.1 – 0.3/2 x 2 = 3.8 m

There’re 4 number of walls with width = 0.45 m (along x direction).

Width = 0.45 m

Height of excavation = 0.6 m

Excavation for the wall along y direction

There’re 3 walls having width = 0.45 m

To get more details, go through the following video tutorial.

Lecturer: ADV. LEARNING

The charges of a specific material of utilization rely on the subsequent:

  • Details of tasks and material regarding their characteristic, share and structural function technique.
  • Amount of materials as well as their charges.
  • Outlay of labors along with their earnings.
  • Place of work site along with the lengths from supply and transportation rates.
  • Operating cost and expenses after incorporation.
  • Earnings.

Outlay of materials on supply and on building location: The outlay of materials is assumed as transported on location comprising the transportation regional tariffs and additional rates.

Aim of evaluation of charges:

  • In order to calculate the genuine outlay of each entity of the materials.
  • In order to calculate the efficient utilization of items and procedures in finishing the specific material.
  • In order to calculate the outlay of additional materials that are not presented in the agreement, although have to be calculated in accordance with the guidelines of the discipline.
  • In order to correct the plan of charges because of rise in the outlay of material and labor or because of adjustment in method.

Labor rates:

  • Mason / Brick level I Group INR 100 for each day.
  • Mason / Brick level 2 Group INR 80 for each day.
  • Male mazdoor INR 60 for each day.
  • Female mazdoor INR 60 for each day.
  • Mixing rates of cement mortar INR 16 for each m3.

Download Estimation and Costing in PDF