Estimation of RCC Framed Building
In the plan, there’re two rooms with size 3.5 x 3.5. There’re 6 six columns. Column width = 1 m. Excavation is going to be done up to the ground level. Overall height up to the ground level is 1.5 m. Excavation is going to be done of 1 m.
Earthwork in excavation in foundation.
Initial measure is to compute the overall centerline between the two columns.
Distance = 3.5 m
Column size = 0.3 m
Hence, center to center distance = 3.5 m + 0.3 m/2 x 2 = 3.8 m
From another center to center, overall centerline of 4.1 – 0.3/2 x 2 = 3.8 m
There’re 4 number of walls with width = 0.45 m (along x direction).
Width = 0.45 m
Height of excavation = 0.6 m
Excavation for the wall along y direction
There’re 3 walls having width = 0.45 m
To get more details, go through the following video tutorial.
Lecturer: ADV. LEARNING
The charges of a specific material of utilization rely on the subsequent:
- Details of tasks and material regarding their characteristic, share and structural function technique.
- Amount of materials as well as their charges.
- Outlay of labors along with their earnings.
- Place of work site along with the lengths from supply and transportation rates.
- Operating cost and expenses after incorporation.
- Earnings.
Outlay of materials on supply and on building location: The outlay of materials is assumed as transported on location comprising the transportation regional tariffs and additional rates.
Aim of evaluation of charges:
- In order to calculate the genuine outlay of each entity of the materials.
- In order to calculate the efficient utilization of items and procedures in finishing the specific material.
- In order to calculate the outlay of additional materials that are not presented in the agreement, although have to be calculated in accordance with the guidelines of the discipline.
- In order to correct the plan of charges because of rise in the outlay of material and labor or because of adjustment in method.
Labor rates:
- Mason / Brick level I Group INR 100 for each day.
- Mason / Brick level 2 Group INR 80 for each day.
- Male mazdoor INR 60 for each day.
- Female mazdoor INR 60 for each day.
- Mixing rates of cement mortar INR 16 for each m3.
Download Estimation and Costing in PDF