How to calculate the cement quantity for neat cement punning at construction Site

In this civil engineering article, you will get some vital notes to work out the necessary materials for neat cement punning at job site.

What quantity of cement will be required for neat cement? What is neat cement?

Indian patent stone flooring is a sort of flooring that is utilized in wooden flooring. Amalgamation/combination of screed concrete as well as neat cement is called IPS flooring. Furthermore, foam is utilized for addressing/overcoming undulation and eradicating/removing void.

Area contemplated/considered for neat cement punning equal to 100 m2 (10 m x 10 m)

Volume for 100 m2 along with a thickness of 1.5 m

= 10 x 10 x 0.0015 equal to 0.15 m3 (wet)

Augment the volume by 25 percent once dry

= 0.15 + (25 percent of 0.15) equal to 0.19 m3 (dry)

Weight of one cement bag equal to 50 kg

One cement bag volume equal to 0.034 m3

Through unitary method,

For 0.034 m3 volume equal to one bag of cement

1 m3 volume equal to 1/0.034 cement bag

For 0.19 m3 volume equal to 1/0.034 x 0.19 cement bag

equal to 5.59 bags

For additional info view the video:

Lecturer: L & T - Learning Technology

How to calculate the cement quantity for neat cement punning at construction Site